Underground sewage connection to the municipal main completed. 4. CHALLENGES & MITIGATION Delay in Chiller unit delivery (expected delay: 2 weeks). Mitigation:
[Number] Requests for Inspection (RFI) submitted; [Number] approved, [Number] pending minor corrections. 6. Planned Activities for Next Week mep work progress report sample
First-fix containment (cable trays and conduits) completed on Floor 5. | Activity | Unit | Total Qty |
| Activity | Unit | Total Qty | Completed This Period | Cumulative Completed | % Complete | |----------|------|-----------|----------------------|----------------------|-------------| | Chilled water pipe installation (floor 2–3) | LF | 2,500 | 300 | 1,800 | 72% | | Ductwork fabrication & installation (floor 4) | LF | 1,200 | 450 | 450 | 37.5% | | AHU installation (units 1–4) | No. | 4 | 0 | 2 | 50% | | Duct insulation (floor 1) | SF | 8,000 | 2,000 | 8,000 | 100% | 500 | 300 | 1